|
|
|
M&A Engineering Ltd - Re-location & Development Progress PageWe have completed the first phase of our expansion and re-location project. Obviously we are excited about this expansion program and thought it would be a good idea to show our valued customers the development progress as things happen. This new venture has already allowed us to offer a broader and better service to our clients. In the meantime, we will add some progress pictures with some progress comments. The first phase of development included the design and build of a bespoke building which has allowed us to offer a much more elaborate in-house machining capacity; along with a much bigger physical preparation capacity for our in-situ machining service. Our new office and workshop isapproximately 10,000 sq ft, and the workshop area is serviced by a 10 Ton; twin beam overhead crane with a 6 metre lift capacity.
Full access for loading and unloading of a 45ft trailer can easily be accommodated within the workshop. This large development building will be set within 2 acres of land, which will allow adequate further area for our second phase expansion which will occur within 1 - 2 years after completion of the first phase.
CHRONOLOGICAL LOG OF PROGRESS - PLEASE SCROLL DOWN PAGE FOR UPDATES.
View from development area - looking West The first day - Tuesday 16th June 2008
It is estimated that some 55,000 Tonnes of soil/sub-soil/stone will be handled in total.
A continuous flow of six 20 Ton lorries is now permitting the removal of 1000 - 1300 Tons per day!
1st August 2008 Reclaiming extra land involved moving a natural stream and filling with approx 10,000 Tonnes of material.
15th August 2008
28th August 2008 Below shows the reclaimed area complete! This has increased the site area by approx 8%
15th Jan 2009 Workshop Foundations - THE FIRST POUR! (and blimey, did it pour) Looking down the back line of the workshop.
20th Jan 2009 Workshop Foundations - THE LAST POUR! Looking down the front line of the workshop.
20th Jan 2009 20th Jan 2009 16th February 2009
4th March 2009
23rd April 2009 Installation and commissioning of the 10 Ton Overhead Crane (Shown with test weights)
11th May 2009 Ready for windows and doors.
Please re-visit from time to time to view site up-dates.
|
|
|









