new building - M&A launches new heavy shop facilities following new HQ opening

M&A Engineering Ltd - Re-location & Development Progress Page

We have completed the first phase of our expansion and re-location project.

Obviously we are excited about this expansion program and thought it would be a good idea to show our valued customers the development progress as things happen. This new venture has already allowed us to offer a broader and better service to our clients. In the meantime, we will add some progress pictures with some progress comments.

The first phase of development included the design and build of a bespoke building which has allowed us to offer a much more elaborate in-house machining capacity; along with a much bigger physical preparation capacity for our in-situ machining service. Our new office and workshop isapproximately 10,000 sq ft, and the workshop area is serviced by a 10 Ton; twin beam overhead crane with a 6 metre lift capacity.

 

3D image of the new M&A Engineering (1st phase) building

Full access for loading and unloading of a 45ft trailer can easily be accommodated within the workshop.

This large development building will be set within 2 acres of land, which will allow adequate further area for our second phase expansion which will occur within 1 - 2 years after completion of the first phase.

 

CHRONOLOGICAL LOG OF PROGRESS - PLEASE SCROLL DOWN PAGE FOR UPDATES.
Last update - 20th Jan 2009

View from development prior to ground works

View from development area - looking West

The first day - Tuesday 16th June 2008

First day of many to level the new site


First update - 17th July 2008. One month on; and approximately 50% of work is completed to level the site.

It is estimated that some 55,000 Tonnes of soil/sub-soil/stone will be handled in total.

Ongoing works to level the new M&A Engineering site   General view of new M&A Engineering site

A continuous flow of six 20 Ton lorries is now permitting the removal of 1000 - 1300 Tons per day!

 

1st August 2008

Reclaiming extra land involved moving a natural stream and filling with approx 10,000 Tonnes of material.
Place mouse over pictures for more details.

Looking down the site over reclaimation area   Looking up the reclaimation area, prior to works

15th August 2008

Looking down reclaimation area - during works   Looking up - works 75% complete

28th August 2008

Below shows the reclaimed area complete! This has increased the site area by approx 8%

Reclaimed area - complete

 

15th Jan 2009

Workshop Foundations - THE FIRST POUR! (and blimey, did it pour)

'West Haven Construction' has been awarded a significant part of all construction works.
Complements go to their team who have continued excellent progress under very inclement
weather conditions.

Looking down the back line of the workshop.
This shows the foundations and steel stanchion pads. These pads
show the template frameworks for ensuring the large bolts are pre-placed accurately before
the concrete is poured. Some of these pads required 6 cubic metres of concrete each!

M&A's New Workshop Foundations - the first pour!

20th Jan 2009

Workshop Foundations - THE LAST POUR!

Looking down the front line of the workshop.
This picture shows the last part of the foundations to be concreted. This was the point
of access for the concrete lorries for the workshop foundations. This will complete the
new workshop foundations and then the setting out of the offices will begin.

Last part of M&A workshop foundations to be concreted.

20th Jan 2009
Opposite view of the above. The last workshop pad is filled.
One pocket and a ten run remains, then the workshop foundation is complete!

20th Jan 2009
The workshop foundations are complete!
The completion of the workshop foundations.

16th February 2009
The first two stanchions are bolted into place.

Workshop Stanchions

4th March 2009
Framework 90% complete

Office and Workshop

Preparing for dwarf wall and external cladding

 

23rd April 2009

Installation and commissioning of the 10 Ton Overhead Crane (Shown with test weights)

10 Ton Overhead Crane will service the whole workshop

11th May 2009

Ready for windows and doors.

Windows and doors - next

 

Please re-visit from time to time to view site up-dates.

 

 

 

 